Handling BIG-BAGs
Functional Description - BIG-BAG Emptying Sequence
1.) Transport big bags by forklift. Lift onto big bag discharge hopper with forklift or on-site crane
2.) Fix BIG-BAG in the discharge position.
3.) Lower the BIG-BAG onto the circular slitting blade fitted on top. Underneath of big bag is slit open automatically under its own weight.
4.) Lift the emptied BIG-BAG, and swing it aside and lower it with the crane or forklift.
Detailed View:
Flow Sheet BIB-BAG Emptying and Pneumatic Conveying Plant (pop-up)
The effective discharge time depends on local handling systems and the flow characteristics and quality of the product contained in the BIG-BAG.
Machinery and components to handle BIG-BAGs
Telschig combines and engineers standard plants and components to produce a solution for your particular situation. See below an overview about the available products and it's capacities.
| Type | BIG-BAG Size | Function | Capacity | Photo |
|---|---|---|---|---|
| Cembag mobile | 0,5 - 2,0t | opening and emptying of big-bags | 10-50 t/h | ![]() |
| Cembag | 0,5 - 2,0t | opening and emptying of big-bags | 10-50 t/h | ![]() |
| Cemtrans | -- | opening and pneumatic conveying from A to B | 10t/h, 25t/h, 35t/h | ![]() |
| Cembreak | -- | destroying of lumps | 10-75 t/h | ![]() |