Handling BIG-BAGs
Functional Description - BIG-BAG Emptying Sequence
1.) Transport big bags by forklift. Lift onto big bag discharge hopper with forklift or on-site crane
2.) Fix BIG-BAG in the discharge position.
3.) Lower the BIG-BAG onto the circular slitting blade fitted on top. Underneath of big bag is slit open automatically under its own weight.
4.) Lift the emptied BIG-BAG, and swing it aside and lower it with the crane or forklift.
The effective discharge time depends on local handling systems and the flow characteristics and quality of the product contained in the BIG-BAG.
Machinery and components to handle BIG-BAGs
Telschig combines and engineers standard plants and components to produce a solution for your particular situation. See below an overview about the available products and it's capacities.
| Type | BIG-BAG Size | Function | Capacity | Photo |
|---|---|---|---|---|
| Cembag mobile | 0,5 - 2,0t | opening and emptying of big-bags | 10-50 t/h | |
| Cembag | 0,5 - 2,0t | opening and emptying of big-bags | 10-50 t/h | ![]() |
| Cemtrans | -- | opening and pneumatic conveying from A to B | 10t/h, 25t/h, 35t/h | ![]() |
| Cembreak | -- | destroying of lumps | 10-75 t/h | ![]() |